Friday, June 18, 2010

Landscaping

Its been a while since the last update. A lot of work has been completed outside the house. Below are some pics of driveway and the backyard.

1. Pathway - This will be the entrance from the pedestrian gate.


2. Driveway. This still needs to be cut.

3. Driveway and pathway from the side of the house.
4. Backyard
5. Steps from the backyard to ground level.




















Thursday, May 13, 2010

Appliances

Appliances will be installed on wed. - Hot water, stove, dishwasher insinkerator.
Keys and remote control to the garage will be handed over at settlement
Heating will be comissioned after settlement, the guys will call us and organise a time. They will run through the controls with us.

Final Inspection

We had the final inspection this morning and the house now looks really cool. Its been cleaned up from inside. There is not too many things to fix now, atleast nothing major.
Following was observed today that needs to be addressed before settlement:
  • Minor paint touchups and cleaning throughout.
  • Tap in kitchen to be replaced to veggie spray.
  • Some flyscreens are inside out.
  • Bifold door does not close properly and needs a handle.
  • Main water pipe to the house to be underground and is also leaking.
  • Render to portico needs paint touch up where the balcony drain is.
  • Soap holders in all bathrooms are upside down.
Termite treatment is a reticulated treatment these days, there is a pipe that runs (underground) through the perimeter of the house and weeps for about 12 months and then you top up the fluid. Cool!!
They had a huge pile of dirt in the front this morning, they are going to level the sides a bit more towards where the retaining wall is.

Wednesday, April 28, 2010

Carpets laid




Carpeting has been completed. The house now looks almost finished and after the carpets been laid it looks completely different.

Tuesday, April 27, 2010

Autumn



  • Carpeting will be started and completed today.
  • Alfresco and garage ceiling completed
  • Balcony tiling completed
  • Retaining walls built
  • Flyscreen doors and windows installed.
  • Pot drawer in pantry installed


Wednesday, April 14, 2010

Plumbing

Plummers are onsite and have completed the taps and basins. Tomorrow they will install the shower screens.
Door handles and door knobs have also been fitted.

Friday, April 9, 2010

Splashback

Shelves have been installed in all the wardrobes, Walk in robe and pantry. Below is a pic of the master WIRSplash back in the kitchen has been installed.

Monday, April 5, 2010

Minor updates

Few updates:
* Two coats of paint have been completed throughout. Rumpus looks cool with the dark brown colour.
* Tiler will commence tiling the main areas now
* Garage roof completed
* Down pipes connected
I was surprised they worked for 2 days during the easter break.

Tuesday, March 30, 2010

Tiling

The tiler has commenced tiling and so far all the shower areas have been completed.

Laundry

Bathroom 2


Master ensuite


Rain water

During the recent rain water has seeped in through the roof tiles into the rumpus. I got a glimpse through the batten holder and two holes where the roof tiles are not fitter together can be seen. I have advised the supervisor to get this fixed up and access if the plaster needs to be redone. But it does not look like any plaster needs to be repaired.







Sunday, March 21, 2010

Painting has started

Its been a while since I updated with a picture of the front of the house. So here it is ..




Painters have commenced painting and should be completed this week. Painters started on Sat morning and when we checked in the evening they had covered the whole house with one coat along with the first coat on all the internal doors.

We are told the roof tiles will go in tomorrow (monday). Once the painting is completed next will be tiling.

Sunday, March 14, 2010

Fix stage completed

The fix stage is complete with all internal doors hung, cabinets installed and portico and balcony rendered. The house is now locked up and we cannot get into the house unless there is someone working onsite who has the keys. This morning they completed the roof of the garage.
I think the next step will be to paint the house followed by tiling. Balcony floor still to be done.

Tuesday, March 9, 2010

Hail storms

All the internal doors have been hung - almost all except for a couple and they have started on the architraves. Went to the house after the big hail storm and was glad there is no hail damage and no leaks etc. The good thing now is that the work is not weather dependent as all the work is to be done inside and the tradies can work even if it rains, so hopefully there wont be any weather related delays. In this week we expect to see the internal doors, shelves, skirting and architraves completed.

Thursday, March 4, 2010

Fix Stage started

All the cabinets in the kitchen and the 3 bathrooms were installed today. Basins and sinks have been delivered but not installed yet. It has now really started to take shape and is looking more and more like a house and gives a real feel of how the final product will look like. All the internal room and cupboard doors were delivered today and most likely will be installed within the next couple of days. All the shelving in the walkin robes, pantry and various cupboard will also be installed in this time frame.
The entire site has been cleared of all rubbish, I think they got a bob cat onsite this morning and clean up the site.
Current Issue: Niche in the study is missing and I have advised the supervisor to get that rectified.

Tuesday, March 2, 2010

Progress

A lot of changes will be happening in the next two weeks.
The ladder going upstairs has been removed and stairs will be installed today. All the material for the stairs is onsite and the guys to install it also arrived this morning.
Cabinets for the kitchen and bathrooms will likely be installed on Thu and internal doors will be hung this week as well. Carpenter will be back by end of week to install all the internal shelves etc.
Painting should start mid march and is expected to continue for 7-8 days followed by tiling.
Fotos of stairs to follow soon.

Friday, February 26, 2010

Some more updates

Plastering is currently in progress. Upstairs is completely plastered. Downstairs is almost plastered with a few rooms needing skirting. They have also started washing the bricks from outside and its coming up really well. All the cement and dirt marks have disappeared.
The bulkhead in the laundry has not been reduced but I measured the height from the floor to the bulkhead and it should fit a top loader machine plus dryer so I will leave the bulkhead as it is.
Missing - the niche in the study is missing and the wall has been plastered, will have to advise supervisor.
Found out what the plaster board in the wet areas is blue compared to white everywhere else - waterproofing.
Scaffolding is still up as a few bricks and roof tiles still need to be done.

Master bedroom photo:


Tuesday, February 16, 2010

Photos

Photos in order: Master bedroom balcony, kitchen/dining, family room







Lockup Completed

Lockup stage is complete. Entire house has been bricked. All external doors have been hung except the master bedroom balcony which will get done when the scaffolding is removed.
Plastering the inside commenced this morning. A lot of the downstairs has been plastered.Saw the guys installing the solar panel and evaporative cooling unit on the roof this morning. Photos for that to follow.

Monday, February 15, 2010

Minor Updates

Some minor updates:
  • Brickies are now completing the upper storey. Almost done- the sides have been bricked.
  • The big glass door in the master bedroom will be put in after the scaffolding has been removed.
  • The missing window in the stairwell has now been fitted.
  • Still missing the speaker cables. Plaster will start going in on wed and take a couple of days. I have called and advised the supervisor that the speaker cables are still not in. He will call the electricians and chase them up.
More photos to follow in a couple of days.