Thursday, January 21, 2010

Friday, January 15, 2010

Bricks

The brickies were at the property this morning. They were sorting out the bricks and organising. If sand is delivered today they will start laying tomorrow or Monday. It will take about a month for the entire house to be bricked. In the mean time over the next 2-3 weeks electricians, gas fitters etc will be working on the inside before the plaster goes on.

Thursday, January 14, 2010

Happy New Year

Its been a month since the last post so welcome back. We got the brick delivered yesterday and work should commence on the house next week. The next task is to lay the bricks followed by all the doors and windows after which the house will achieve lockup stage. Once the bricks are laid to a certain height they will also start hanging the plaster inside.