Wednesday, April 28, 2010

Carpets laid




Carpeting has been completed. The house now looks almost finished and after the carpets been laid it looks completely different.

Tuesday, April 27, 2010

Autumn



  • Carpeting will be started and completed today.
  • Alfresco and garage ceiling completed
  • Balcony tiling completed
  • Retaining walls built
  • Flyscreen doors and windows installed.
  • Pot drawer in pantry installed


Wednesday, April 14, 2010

Plumbing

Plummers are onsite and have completed the taps and basins. Tomorrow they will install the shower screens.
Door handles and door knobs have also been fitted.

Friday, April 9, 2010

Splashback

Shelves have been installed in all the wardrobes, Walk in robe and pantry. Below is a pic of the master WIRSplash back in the kitchen has been installed.

Monday, April 5, 2010

Minor updates

Few updates:
* Two coats of paint have been completed throughout. Rumpus looks cool with the dark brown colour.
* Tiler will commence tiling the main areas now
* Garage roof completed
* Down pipes connected
I was surprised they worked for 2 days during the easter break.