All the cabinets in the kitchen and the 3 bathrooms were installed today. Basins and sinks have been delivered but not installed yet. It has now really started to take shape and is looking more and more like a house and gives a real feel of how the final product will look like. All the internal room and cupboard doors were delivered today and most likely will be installed within the next couple of days. All the shelving in the walkin robes, pantry and various cupboard will also be installed in this time frame.
The entire site has been cleared of all rubbish, I think they got a bob cat onsite this morning and clean up the site.
Current Issue: Niche in the study is missing and I have advised the supervisor to get that rectified.