Its been a while since the last update. A lot of work has been completed outside the house. Below are some pics of driveway and the backyard.
1. Pathway - This will be the entrance from the pedestrian gate.
2. Driveway. This still needs to be cut.
Friday, June 18, 2010
Thursday, May 13, 2010
Appliances
Appliances will be installed on wed. - Hot water, stove, dishwasher insinkerator.
Keys and remote control to the garage will be handed over at settlement
Heating will be comissioned after settlement, the guys will call us and organise a time. They will run through the controls with us.
Keys and remote control to the garage will be handed over at settlement
Heating will be comissioned after settlement, the guys will call us and organise a time. They will run through the controls with us.
Final Inspection
We had the final inspection this morning and the house now looks really cool. Its been cleaned up from inside. There is not too many things to fix now, atleast nothing major.
Following was observed today that needs to be addressed before settlement:
They had a huge pile of dirt in the front this morning, they are going to level the sides a bit more towards where the retaining wall is.
Following was observed today that needs to be addressed before settlement:
- Minor paint touchups and cleaning throughout.
- Tap in kitchen to be replaced to veggie spray.
- Some flyscreens are inside out.
- Bifold door does not close properly and needs a handle.
- Main water pipe to the house to be underground and is also leaking.
- Render to portico needs paint touch up where the balcony drain is.
- Soap holders in all bathrooms are upside down.
They had a huge pile of dirt in the front this morning, they are going to level the sides a bit more towards where the retaining wall is.
Wednesday, April 28, 2010
Tuesday, April 27, 2010
Autumn
Wednesday, April 14, 2010
Plumbing
Plummers are onsite and have completed the taps and basins. Tomorrow they will install the shower screens.
Door handles and door knobs have also been fitted.
Door handles and door knobs have also been fitted.
Friday, April 9, 2010
Splashback
Monday, April 5, 2010
Minor updates
Few updates:
* Two coats of paint have been completed throughout. Rumpus looks cool with the dark brown colour.
* Tiler will commence tiling the main areas now
* Garage roof completed
* Down pipes connected
I was surprised they worked for 2 days during the easter break.
* Two coats of paint have been completed throughout. Rumpus looks cool with the dark brown colour.
* Tiler will commence tiling the main areas now
* Garage roof completed
* Down pipes connected
I was surprised they worked for 2 days during the easter break.
Tuesday, March 30, 2010
Rain water
During the recent rain water has seeped in through the roof tiles into the rumpus. I got a glimpse through the batten holder and two holes where the roof tiles are not fitter together can be seen. I have advised the supervisor to get this fixed up and access if the plaster needs to be redone. But it does not look like any plaster needs to be repaired.
Sunday, March 21, 2010
Painting has started
Its been a while since I updated with a picture of the front of the house. So here it is ..
Painters have commenced painting and should be completed this week. Painters started on Sat morning and when we checked in the evening they had covered the whole house with one coat along with the first coat on all the internal doors.
We are told the roof tiles will go in tomorrow (monday). Once the painting is completed next will be tiling.
Sunday, March 14, 2010
Fix stage completed
The fix stage is complete with all internal doors hung, cabinets installed and portico and balcony rendered. The house is now locked up and we cannot get into the house unless there is someone working onsite who has the keys. This morning they completed the roof of the garage.
I think the next step will be to paint the house followed by tiling. Balcony floor still to be done.
Tuesday, March 9, 2010
Hail storms
All the internal doors have been hung - almost all except for a couple and they have started on the architraves. Went to the house after the big hail storm and was glad there is no hail damage and no leaks etc. The good thing now is that the work is not weather dependent as all the work is to be done inside and the tradies can work even if it rains, so hopefully there wont be any weather related delays. In this week we expect to see the internal doors, shelves, skirting and architraves completed.
Thursday, March 4, 2010
Fix Stage started
All the cabinets in the kitchen and the 3 bathrooms were installed today. Basins and sinks have been delivered but not installed yet. It has now really started to take shape and is looking more and more like a house and gives a real feel of how the final product will look like. All the internal room and cupboard doors were delivered today and most likely will be installed within the next couple of days. All the shelving in the walkin robes, pantry and various cupboard will also be installed in this time frame.
The entire site has been cleared of all rubbish, I think they got a bob cat onsite this morning and clean up the site.
Current Issue: Niche in the study is missing and I have advised the supervisor to get that rectified.
The entire site has been cleared of all rubbish, I think they got a bob cat onsite this morning and clean up the site.
Current Issue: Niche in the study is missing and I have advised the supervisor to get that rectified.
Wednesday, March 3, 2010
Tuesday, March 2, 2010
Progress
A lot of changes will be happening in the next two weeks.
The ladder going upstairs has been removed and stairs will be installed today. All the material for the stairs is onsite and the guys to install it also arrived this morning.
Cabinets for the kitchen and bathrooms will likely be installed on Thu and internal doors will be hung this week as well. Carpenter will be back by end of week to install all the internal shelves etc.
Painting should start mid march and is expected to continue for 7-8 days followed by tiling.
Fotos of stairs to follow soon.
The ladder going upstairs has been removed and stairs will be installed today. All the material for the stairs is onsite and the guys to install it also arrived this morning.
Cabinets for the kitchen and bathrooms will likely be installed on Thu and internal doors will be hung this week as well. Carpenter will be back by end of week to install all the internal shelves etc.
Painting should start mid march and is expected to continue for 7-8 days followed by tiling.
Fotos of stairs to follow soon.
Friday, February 26, 2010
Some more updates
Plastering is currently in progress. Upstairs is completely plastered. Downstairs is almost plastered with a few rooms needing skirting. They have also started washing the bricks from outside and its coming up really well. All the cement and dirt marks have disappeared.
The bulkhead in the laundry has not been reduced but I measured the height from the floor to the bulkhead and it should fit a top loader machine plus dryer so I will leave the bulkhead as it is.
Missing - the niche in the study is missing and the wall has been plastered, will have to advise supervisor.
Found out what the plaster board in the wet areas is blue compared to white everywhere else - waterproofing.
Scaffolding is still up as a few bricks and roof tiles still need to be done.
Master bedroom photo:
The bulkhead in the laundry has not been reduced but I measured the height from the floor to the bulkhead and it should fit a top loader machine plus dryer so I will leave the bulkhead as it is.
Missing - the niche in the study is missing and the wall has been plastered, will have to advise supervisor.
Found out what the plaster board in the wet areas is blue compared to white everywhere else - waterproofing.
Scaffolding is still up as a few bricks and roof tiles still need to be done.
Master bedroom photo:
Tuesday, February 16, 2010
Lockup Completed
Lockup stage is complete. Entire house has been bricked. All external doors have been hung except the master bedroom balcony which will get done when the scaffolding is removed.
Plastering the inside commenced this morning. A lot of the downstairs has been plastered.Saw the guys installing the solar panel and evaporative cooling unit on the roof this morning. Photos for that to follow.
Plastering the inside commenced this morning. A lot of the downstairs has been plastered.Saw the guys installing the solar panel and evaporative cooling unit on the roof this morning. Photos for that to follow.
Monday, February 15, 2010
Minor Updates
Some minor updates:
- Brickies are now completing the upper storey. Almost done- the sides have been bricked.
- The big glass door in the master bedroom will be put in after the scaffolding has been removed.
- The missing window in the stairwell has now been fitted.
- Still missing the speaker cables. Plaster will start going in on wed and take a couple of days. I have called and advised the supervisor that the speaker cables are still not in. He will call the electricians and chase them up.
Sunday, February 7, 2010
Insulation
Insulation to the entire house has been completed yesterday.
Two different types of insulation have been used - one for the ceiling upstairs and one for the exterior wall. The one used for the exterior walls provides sound insulation from outside too. It took the insulators a full day to complete the job. They contract through CSR who have the contract for PD.
Upstairs Family Room:
Rumpus Insulated:
Friday, February 5, 2010
Ducts installed
Bath tub in the upstairs bathroom has been placed in the bathroom though not installed yet. Insulation for the ceiling and walls has been delivered. Cant believe that it will need so much insulation, the study room is full of insulation rolls and a few rolls are in the next room. Another layer of plywood has been installed where all the showers will be and drains are in place.
Antenna cable has been run from the rumpus to the roof.
Thursday, February 4, 2010
Tuesday, February 2, 2010
Updates
The following has been completed:
* Ground floor is completely bricked
* Electrical cables and data cables have been laid throughout the house
* Plumbing works completed
* The guy to install ducted vacuum was onsite today to install the ducts. There will be 3points downstairs plus the dust pan, 2 points upstairs and the unit in the garage will also have a point which will be handy to vacuum the cars or garage.
Ducted vacuum ducts for the ground floor go up to the second floor and then into the garage where the unit is. Only if the house is on stumps, the ducts can go under the floor on ground floor.
Next:
* Scaffolding will go up tomorrow
* Brickies will be back on Fri and will complete the top storey by late next week or early week after.
* Carpenters will be in later in the week to straighten all the frames, add more nails to provide strength to the frame, install the remaining doors and windows.
* It is expected the house will be in lockup stage in a couple of weeks.
Issues:
* The pillar on the alfresco is sitting about an inch out of the slab. Supervisor advised that they will pour concrete underneath.
* The window in the stairwell is missing in the frame. Spoke to supervisor and they will put that in. The window has been delivered but not sure how they managed to omit it in the frame.
* Speaker cables have not been installed along with the electric cables. The electricians may not have yet competed the work, they were here yesterday so they may be coming back today. Either way the supervisor will follow up.
* Ground floor is completely bricked
* Electrical cables and data cables have been laid throughout the house
* Plumbing works completed
* The guy to install ducted vacuum was onsite today to install the ducts. There will be 3points downstairs plus the dust pan, 2 points upstairs and the unit in the garage will also have a point which will be handy to vacuum the cars or garage.
Ducted vacuum ducts for the ground floor go up to the second floor and then into the garage where the unit is. Only if the house is on stumps, the ducts can go under the floor on ground floor.
Next:
* Scaffolding will go up tomorrow
* Brickies will be back on Fri and will complete the top storey by late next week or early week after.
* Carpenters will be in later in the week to straighten all the frames, add more nails to provide strength to the frame, install the remaining doors and windows.
* It is expected the house will be in lockup stage in a couple of weeks.
Issues:
* The pillar on the alfresco is sitting about an inch out of the slab. Supervisor advised that they will pour concrete underneath.
* The window in the stairwell is missing in the frame. Spoke to supervisor and they will put that in. The window has been delivered but not sure how they managed to omit it in the frame.
* Speaker cables have not been installed along with the electric cables. The electricians may not have yet competed the work, they were here yesterday so they may be coming back today. Either way the supervisor will follow up.
Thursday, January 21, 2010
Friday, January 15, 2010
Bricks
The brickies were at the property this morning. They were sorting out the bricks and organising. If sand is delivered today they will start laying tomorrow or Monday. It will take about a month for the entire house to be bricked. In the mean time over the next 2-3 weeks electricians, gas fitters etc will be working on the inside before the plaster goes on.
Thursday, January 14, 2010
Happy New Year
Its been a month since the last post so welcome back. We got the brick delivered yesterday and work should commence on the house next week. The next task is to lay the bricks followed by all the doors and windows after which the house will achieve lockup stage. Once the bricks are laid to a certain height they will also start hanging the plaster inside.
Subscribe to:
Posts (Atom)